AKH Wien
€ 8 Mio.
New construction of intensive care areas in neurological medicine
New construction of an intensive care unit, specialised in the care of neurological patients, on a floor area of approx. 5,000 m² (including: 20 intensive care rooms, several examination and treatment rooms, a Phase B area, specialised EEG areas and follow-up care for stroke-unit patients).
2 images
AKH Wien
€ 3 Mio.
Construction of an intraoperative MRI
Construction of an intraoperative MRI (a combination of MRI and operating theatre) including all required ancillary rooms.
AKH Wien
€ 1,9 Mio.
New construction of an extracorporeal centre and general-care wards
Establishment of an extracorporeal centre on a floor area of approx. 3,500 m².
3 images
AKH Wien
€ 1,9 Mio.
Replacement of the angiography system in the neurology operating theatre
Replacement of the angiography system within the operating theatre area as part of the modernisation of the University Clinic for Neurosurgery.
AKH Wien
€ 1,5 Mio.
Replacement of a planning CT in radiotherapy
New construction of a planning CT including the required surrounding areas (changing room, control room and equipment room). Design and installation of a laser positioning system, a respiratory simulation system and various items of medical equipment.
2 images
AKH Wien
€ 1,2 Mio.
Replacement of a CT system
Replacement of the CT scanner as part of the modernisation of the University Clinic for Neurosurgery.
9 images
AKH Wien
€ 1,1 Mio.
Construction of a ward for approx. 140 beds
Construction of a ward for approx. 140 beds in general care across four levels. Level 03: oncology day clinic, Level 04: oncology, Level 05: haematology, Level 06: palliative care and radiation oncology.
AKH Wien
€ 1 Mio.
Replacement of two uroscopy systems and adaptation of the examination rooms
Replacement of two fluoroscopy systems in separate rooms and adaptation of the rooms to qualify as a "procedure room". Design and installation of medical metal fittings as well as various mobile and fixed medical equipment.
2 images
AKH Wien
€ 550.000
Replacement of a fluoroscopy unit
Replacement of the old device with a modern fluoroscopy system. Enlargement of the examination room and adaptation to the current regulatory requirements. Redesign and modernisation of the control room and the equipment room. Design and installation of medical metal fittings as well as various mobile and fixed
6 images
AKH Wien
€ 500.000
Construction of a medical care centre
Construction of a medical care centre with 9 examination and treatment rooms, a laboratory and a dirty utility room.
AKH Wien
€ 450.000
Replacement of four washer-disinfectors
Removal of four sterilisation systems and installation of modern devices. Adaptation of the existing medical metal fittings in line with the new requirements.
AKH Wien
€ 350.000
Construction of an IMC unit
Construction of an IMC unit with five patient rooms, a nurses' station and various ancillary rooms.
3 images
AKH Wien
€ 280.000
Replacement of an X-ray therapy system
Construction of a modern X-ray therapy system including the required ancillary rooms (equipment room, control room and changing room).
AKH Wien
€ 210.000
Replacement of a steam steriliser
Replacement of the outdated steam steriliser. Renewal of the technical area and the medical metal fittings.
5 images
AKH Wien
€ 170.000
Construction of a simulation room for radiotherapy
Removal of an X-ray therapy device and repurposing of the room into a preparation room for treatments at the linear accelerator (breathing training). The preparation room includes a surface scanner and a LINAC treatment table.
AKH Wien
€ 150.000
Replacement of two washer-disinfectors
Removal of two old devices and installation of a modern washer-disinfector. Division of the project area into a clean and a dirty area. Modernisation of both areas through suitable adaptations to the operational workflow. Design and installation of medical metal fittings as well as various mobile and fixed medical equipment.
3 images
AKH Wien
€ 100.000
Construction of private-class rooms in urology
Conversion of existing urology bed rooms into two private-class rooms, including the construction of a modern dirty utility room.
2 images
AKH Wien
€ 100.000
Construction of private-class rooms in orthopaedics
Conversion of existing orthopaedics bed rooms into three private-class rooms, including the construction of a modern dirty utility room.
AKH Wien
€ 530.000
Conversion of a pathology department and new construction of cold-storage cells
New construction of 39 cold-storage cells as part of the redesign of the entire floor plan, coordinated with the operational workflow. Expansion of the autopsy dissection tables as well as design and installation of medical metal fittings.
AKH Wien
€ 8,5 Mio.
Mother-and-child centre, full fit-out BT61.1
Two operating theatres, an intensive care unit (ICU) and an intermediate care unit (IMCU), as well as a fully equipped radiology department
2 images
AKH Wien
€ 5,6 Mio.
Replacement of a linear accelerator
Replacement of the linear accelerator including the patient positioning system. Modernisation of the control and equipment rooms of the linear accelerator.
4 images
AKH Wien
€ 4,1 Mio.
Replacement of an angiography system and construction of a CT sliding gantry
Replacement of the old angiography system with a biplane system, as well as replacement of the CT scanner with a CT system featuring a sliding gantry. Design and installation of medical metal fittings as well as various mobile and fixed medical equipment.
5 images
AKH Wien
€ 4,1 Mio.
Construction of a hybrid operating theatre
Construction of a hybrid operating theatre. Design and installation of medical metal fittings as well as various mobile and fixed medical equipment (including: heart-lung machine, ventilators, anaesthesia machine, suction systems).
AKH Wien
€ 3,3 Mio.
Modernisation and adaptation of three operating theatres
Modernisation and adaptation of three operating theatres for the use of surgical robots. Design and installation of medical metal fittings as well as various mobile and fixed medical equipment.
2 images
AKH Wien
€ 2,6 Mio.
Replacement of a linear accelerator 2
Replacement of the linear accelerator including the patient positioning system. Modernisation of the control and equipment room of the linear accelerator and adaptation to suit the new system.
AKH Wien
€ 2,5 Mio.
Construction of an intensive care unit with 8 bed spaces
Design and construction of an intensive care unit for eight beds, a POC laboratory, an equipment store, a dirty utility room and further ancillary rooms. Special feature: establishment of the intensive care unit on the former areas of office rooms.
5 images
AKH Wien
€ 2,2 Mio.
Endoscopy operating theatre
Construction of an endoscopy operating theatre. Design and installation of medical metal fittings as well as various mobile and fixed medical equipment.
3 images
AKH Wien
€ 1,9 Mio.
Replacement of an MRI system
Replacement of the old MRI system and modernisation of the preparation room. Modernisation of the control and equipment room. Adaptation of the preparation room for the care of emergency patients. Design and installation of medical metal fittings as well as various mobile and fixed medical equipment
4 images
AKH Wien
€ 1,8 Mio.
Replacement of a PET-CT
Construction of a PET-CT system and an additional workstation for the preparation of radionuclides.
6 images
AKH Wien
€ 1,6 Mio.
Replacement of an angiography system
Replacement of the old angiography system. Adaptation and modernisation of the control room and the equipment room.
2 images
AKH Wien
€ 1,6 Mio.
Replacement of an angiography system 2
Replacement of the old angiography system. Adaptation and modernisation of the control room and the equipment room.
AKH Wien
€ 1,5 Mio.
Modernisation of an 8-bed intensive care unit
Design and construction of an intensive care unit for eight beds, a POC laboratory, an equipment store, a dirty utility room and further ancillary rooms.
AKH Wien
€ 1,2 Mio.
Whole-body PET-CT
Replacement of the existing PET-CT system. Adaptation of the existing examination room, the workstations in the control room and the equipment room.
4 images
AKH Wien
€ 1 Mio.
Replacement of two mattress disinfectors
Replacement of two mattress disinfection systems including adaptation of the medical metal fittings.
9 images
AKH Wien
€ 900.000
Physical medicine modernisation and adaptation
Modernisation and adaptation of the physical therapy department over an area of approx. 1,380 m², including the pain clinic.
3 images
AKH Wien
€ 500.000
Replacement of an X-ray imaging station
Replacement of the existing X-ray system with a new digital system. Design and installation of medical metal fittings as well as various mobile and fixed medical equipment.
2 images
AKH Wien
€ 480.000
New construction of a child and adolescent psychiatry unit
Modernisation of the existing building across six levels. Construction of an extension and the addition of one storey. Design and installation of various mobile and fixed medical equipment (ECG devices, EEG, patient beds, examination couches, defibrillators, etc.).
4 images
AKH Wien
€ 460.000
Replacement of an X-ray imaging station 2
Replacement of the existing X-ray system with a new digital system. Design and installation of medical metal fittings as well as various mobile and fixed medical equipment.
4 images
AKH Wien
€ 450.000
Establishment of ERCP
Replacement of the fluoroscopy device, handling of all regulatory activities relating to laser applications and modernisation of the rest room.
3 images
AKH Wien
€ 350.000
Replacement of an X-ray imaging station 3
Replacement of the existing system with a new digital system.
AKH Wien
€ 330.000
Construction of a bed disinfection system
Conversion of an office area for the construction of a bed disinfection system.
3 images
AKH Wien
€ 250.000
New construction of outpatient areas at the cardiothoracic centre
Construction of an outpatient area (including: transplant centre, examination and treatment rooms as well as areas for cardiac technology) for cardiothoracic surgery patients over an area of approx. 1,900 m².
AKH Wien
€ 150.000
New construction of a recovery room
Construction of a recovery room with three bed positions for the five operating theatres of neurosurgery, as well as a monitoring station for nursing staff and a dirty utility room.
4 images
AKH Wien
€ 150.000
Modernisation of outpatient areas (cardiology and angiology)
Modernisation and restructuring of the outpatient areas of cardiology and angiology (15 rooms).
AKH Wien
€ 150.000
Construction of examination and treatment rooms
Repurposing of a laboratory area into three examination and treatment rooms.
3 images
AKH Wien
€ 100.000
Adaptation of the reprocessing for OP1, OP2 and Z-Steri
Adaptation of the reprocessing systems and conversion of the medical metal fittings so that the surgical instruments of the surgical robots can be cleaned. Conversion of reprocessing systems for two operating theatres and the central sterilisation department.
Schweiz
€ 10 Mio.
Cardio-Neuro Centre Lake Constance, Switzerland
The hospital has 58 beds, 12 observation beds, two operating theatres as well as a hybrid operating theatre and a cardiac catheterisation laboratory, and treats approximately 2,200 inpatients and approximately 6,200 outpatients each year.
5 images
Naher Osten
€ 8 Mio.
Hospital projects in war zones
Over roughly two and a half years on site in crisis and conflict regions in Syria, Jordan and Lebanon: the needs-based equipping of medical facilities under the most challenging conditions – with needs assessments, equipment evaluations, procurement, logistics and the quality assurance of local suppliers.